Drove by today and still no turf? Practice starting next week, and only the small practice field (about half a football field) to practice on. Looks like it might be tough for the tigers to prepare? No home game scheduled until the 3rd game of the year so should be ready?

Link to comment
Share on other sites

 
 
 
 
 
 

I saw the field Sunday. It looks like everything is ready to start laying carpet but there was none in site. Didn't someone say they sent the wrong carpet the first time so now they have to wait?

Link to comment
Share on other sites

 

[ QUOTE ]

I saw the field Sunday. It looks like everything is ready to start laying carpet but there was none in site. Didn't someone say they sent the wrong carpet the first time so now they have to wait?

 

[/ QUOTE ]

 

I beleive I saw the Honaker boys over at SVCC practicing today...anyone know it that was them?

Link to comment
Share on other sites

 
 
 

[ QUOTE ]

[ QUOTE ]

I saw the field Sunday. It looks like everything is ready to start laying carpet but there was none in site. Didn't someone say they sent the wrong carpet the first time so now they have to wait?

 

[/ QUOTE ]

 

I beleive I saw the Honaker boys over at SVCC practicing today...anyone know it that was them?

 

[/ QUOTE ]

 

yeah ...and they won't let us play over there...lol...guess they have some standards.

Link to comment
Share on other sites

 
 

seems like I rem. someone saying somewhere that installation of the turf itself takes 2-3 weeks, so they'll be cuttin' it close (of course, it shouldn't be much of a problem/hassle to change it around & play R away this year and home next year - that'll givem 2 more weeks).

Link to comment
Share on other sites

 
 

I heard that originally turf company was supposed to be there in early July, but the contractor ran into some unexpected things under the field which delayed their end of things thus pushing the turf back. I think now turf company is rearranging things to get people in to make sure field is done. I doubt there will be any suing going on, just some unexpected circumstances that threw off the logistics.

Link to comment
Share on other sites

 

[ QUOTE ]

seems like I rem. someone saying somewhere that installation of the turf itself takes 2-3 weeks, so they'll be cuttin' it close (of course, it shouldn't be much of a problem/hassle to change it around & play R away this year and home next year - that'll givem 2 more weeks).

 

[/ QUOTE ]

Actually that would be a hassle. The idea is to dedicate the field at Honaker this year against Richlands, then dedicate the field at Richlands next year against Honaker.

Link to comment
Share on other sites

 

[ QUOTE ]

I heard that originally turf company was supposed to be there in early July, but the contractor ran into some unexpected things under the field which delayed their end of things thus pushing the turf back.

 

[/ QUOTE ]

I don't think that running into ROCK at Honaker qualifies as unexpected.

Link to comment
Share on other sites

 
 
 

The turf has been rolled out on the field. Orange End Zones and Green with lines, no numbers or lettering yet. Just rolled out it looks good. Can't wait to see the finished product.

Link to comment
Share on other sites

 
 

Join the conversation

You can post now and register later. If you have an account, sign in now to post with your account.

Guest
Reply to this topic...

×   Pasted as rich text.   Paste as plain text instead

  Only 75 emoji are allowed.

×   Your link has been automatically embedded.   Display as a link instead

×   Your previous content has been restored.   Clear editor

×   You cannot paste images directly. Upload or insert images from URL.

Loading...
 Share

×
×
  • Create New...